Boston, MA |
|
|
Duration of Project: |
24 Months |
|
|
Date of Completion: |
December 2004 |
|
|
Project Team: |
|
|
|
Client/Owner: |
Trinity Church in
the City of Boston |
|
|
Architect: |
Goody Clancy |
|
|
General Contractor: |
Shawmut Design and
Construction |
|
|
Structural Engineer: |
LeMessurier
Consultants |
|
|
MEP Engineer: |
Cosentini
Associates |
|
|
Leggat McCall Scope: Leggat McCall was
engaged to assist the volunteer building committee in its role as manager of
the execution phase of a plan that had been several years in the planning and
design phase. |
||
|
Project Profile: ·
Restoration of exterior of tower including clay tile roof repairs,
extensive stone repair and replacement, window replacement and lead work. ·
Establishment of program and bookshop space in Church lower level by
reduction of floor level, water proofing of foundation, repair of 1877 wooden
piles and pile caps and acoustical separation of new space for sanctuary. |
||