Trinity Church in the City of Boston

Boston, MA


 

Duration of Project:

24 Months

Date of Completion:

December 2004

Project Team:

 

Client/Owner:

Trinity Church in the City of Boston

Architect:

Goody Clancy

General Contractor:

Shawmut Design and Construction

Structural Engineer:

LeMessurier Consultants

MEP Engineer:

Cosentini Associates

Leggat McCall Scope:

Leggat McCall was engaged to assist the volunteer building committee in its role as manager of the execution phase of a plan that had been several years in the planning and design phase.

Project Profile:

·         Restoration of exterior of tower including clay tile roof repairs, extensive stone repair and replacement, window replacement and lead work.

·         Establishment of program and bookshop space in Church lower level by reduction of floor level, water proofing of foundation, repair of 1877 wooden piles and pile caps and acoustical separation of new space for sanctuary.