Property Type: |
Hospital |
|
|
Project Size: |
100,000 SF New 570 New Parking
Spaces 13,000 SF Building
Relocation & Renovation |
|
|
Year Started/Completed: |
2005/2007 |
|
|
Project Team: |
|
|
|
Client / Owner: |
Partners Healthcare |
|
|
Architect: |
|
|
|
General Contractor: |
Turner Construction |
|
|
Structural Engineer: |
Souza & True |
|
|
MEP Engineer: |
|
|
|
Leggat McCall Scope: Manage all aspects of the project from site
enabling package / execution and building movers
contract negotiation through project completion and turnover. |
||
|
Project Profile: ·
Move existing turn-of-the-century historical medical office building
to make way for new emergency department addition. ·
Add 570 parking spaces to existing cast in place concrete parking
garage while keeping the garage fully operational. ·
Build new 100,000 SF addition, including new emergency department fitout on top of functional operating rooms. |
||