Epstein Becker & Green

Boston, MA


 

Project Size:

50,000 SF

Duration of Project:

15 Months

Date of Completion:

February 2002

Project Team:

 

Owner

Boston Properties

Architect:

CBT/Childs Bertman Tseckares

General Contractor:

Shawmut Design and Construction

MEP Engineer:

TMP Consulting Engineers

Telecommunications:

ETG

A/V:

Acentech Incorporated

Leggat McCall Scope:

Manage architectural selection, general contractor selection and design process for 27,000 SF of initial occupancy and 13,000 SF of built-out sublet space.

Project Profile:

·         Extremely high-end finishes

·         3,200 SF conference center incorporating multiple conference rooms, catering area and break-out space

·         Wireless connectivity throughout space

·         Custom interconnecting stair