“Leggat McCall
Properties pulled the design and construction team together like they were
employees of the Exchange. We couldn’t
have done it without them.” Edward J. Lesser Executive Vice President Boston Stock Exchange
|
Boston Stock
Exchange, Inc. Boston, MA |
|
|
Project Size: |
40,000 SF |
|
|
Duration of Project: |
32 Months |
|
|
Date of Completion: |
February 1999 |
|
|
Project Team: |
|
|
|
Architect: |
CBT/Childs Bertman
Tseckares |
|
|
General Contractor: |
Payton Construction
Corporation |
|
|
MEP Engineer: |
Cosentini
Associates |
|
|
Telecommunications: |
Cosentini
Information Technologies |
|
|
Trading Posts: |
Woodtronics |
|
|
Workstations/Casegoods: |
Creative Office
Pavilion |
|
|
A/V: |
Nicholas Browse
& Associates |
|
|
Marketing/Gallery Design: |
Stable
Productions/Planter Interactive |
|
|
Leggat McCall Scope: Seamlessly design, construct and move the Boston
Stock Exchange with all of its technical aspects into a historic building in Boston’s
Financial District including management of the execution of the base building
and interior redevelopment, performance of site and building due diligence
(floor loads, electrical capacity, HVAC, structural and environmental) on all
potential locations. |
||
|
Project Profile: ·
40,000 SF project with 100 trading stations, conference rooms, vaults
and office space |
||